Skip to content
RALTIQO Engineering

2025 / Commissioning

ACE Supplier

AVR replacement and generator load-sharing checks

Replacement and calibration of the DG5 automatic voltage regulator, with protection and load-sharing checks.

Discipline
Power generation & distribution
Period
2025

Technical scope

Work and verification

  1. 01

    Verification of generator wiring and DECS-100 regulator configuration.

  2. 02

    Offline adjustment and tests with changing onboard loads.

  3. 03

    Checks of parallel operation and selected generator-protection functions.

Documented outcome

Calibration and load-sharing test records are available. Test limitations at the highest loads were recorded.

Engineering support

Let's discuss your next scope.

Tell us the equipment type, location, symptoms and required timing. Drawings, alarm records and service history help assess the work.